2002
- 1 January ID23 received first round funding
- 5 March Detailed floor plans completed and signed
- 20 December Cabins and lead hutches completed
2003
- 12 February optical hutch radiation test completed
- 11 March installation of the primary slits completed
- 23 May first X-ray beam in the optic hutch (primary slits commissioning)
- 20 June experimental hutch radiation test completed
- 25 October first data set collected
- 5 November toroidal miror installed
2004
- 12 March diffractometer installed and prealigned
- 16 March slit box installed and aligned
2005
- 18 January final toroidal mirror installed
- 12 January installation of the final detector translation
- 11 April installation of the fast piezo shutter
- 25 August installation automatic sample changer
- 3 October installation of the ADSC Q315 detector
2006